§ 18.10.020. Application for bonus.
Latest version.
General contractors or subcontractors desiring to apply for the local hire bonus must notify the owner in writing of his intent to apply within 10 days of the notice to proceed and must submit the complete application on the form provided for by the mayor at the time of filing the notice of completion. If the contractor or subcontractor fails to give notice of intent to apply for the bonus as required by this section, the contractor or subcontractor will no longer be eligible for the bonus.
(Ord. No. 86-13, § 1(part), 1986; Ord. No. 83-21, § 1(part), 1983)